2021 Street Resurfacing Program

   
Tentative Start Date: Late April/Early May 2021
Tentative Completion Date: Late July/Early August 2021
Bid Opening: 3/16/2021
Project Manager: Bill Suchecki, Public Works
Contractor: Schroeder Asphalt Service, INC
Awarded Contract Amount: $864,042.05
Funding Sources: Motor Fuel Tax (MFT) and Local Funds

Project Information

The work to be performed consists of storm sewer improvements, curb and gutter removal and replacement, sidewalk removal and replacement, asphalt surface removal, pavement base patching, asphalt leveling binder, asphalt surface course, pavement markings and parkway restoration.

Construction Limits

Josephine Ct, Mallory Ct, Lisa Ct, Crestwood Ln (Dawngate - Creekside), California Ct, Woodland Ct, California Av (Tall Oaks - Dawngate0, McKone Ct, Woodcliff Ct, Chas Dr, Keystone Ct, Stork Ct, Hoover St, Hoover Ct, and Swallow Ln.

Anticipated Hours of Work:

7:00 AM - 6:00 PM Monday - Friday (Saturday if necessary)


       

Click on Map for larger image

2021 Resurface

Weekly Project Update

10/14/2021: Project substantially complete.  Parkway overseeding at various locations with poor grass establishment expected to take place prior to end of fall season.  
 
 NOTE:  Please allow parkway seeding and straw blanket areas to establish by not mowing until substantial growth is evident, 3+ inches.  When mowing resumes, raise height of mower deck to prevent scalping and blanket tear.  Straw blanket should remain in place until full grass establishment.  Straw blanket will biodegrade naturally.

Construction Notifications