2022 Street Resurfacing Program

   
Tentative Start Date: Late June 2022
Tentative Completion Date: September 2022
Bid Opening: 3/15/2022
Project Manager: Joel Benton, Rolling Meadows Public Works
Contractor: Builders Paving, LLC.
Awarded Contract Amount: $1,178,000.00
Funding Sources: Motor Fuel Tax (MFT) and Local Funds

Project Information

The work to be performed consists of storm sewer improvements, curb and gutter removal and replacement, sidewalk removal and replacement, asphalt surface removal, pavement base patching, asphalt leveling binder, asphalt surface course, pavement markings and parkway restoration.

Construction Limits

Dove Street (St. James to Campbell)

Eastman Street (Meadow to Dove)

Wing Street (Meadow to Dove)

Jay Lane (Central to Hawk)


Anticipated Hours of Work:

7:00 AM - 6:00 PM Monday - Friday (Saturday if necessary)


       

Weekly Project Update


Construction Notifications