Arbor Drive Water Main Improvements Phase 1

   
Tentative Start Date: April 8, 2019
Tentative Completion Date: June 28, 2019
Bid Opening: March 12, 2019
Project Manager: San Seveska, RMPW Utilities Superintendent
Contractor: Patnick Construction
Awarded Contract Amount: $650,037.50
Funding Sources: Local, Utilities Fund

Project Information

The work includes the construction of approximately 2,060 feet of 12-inch ductile iron water main installation, approximately 160 feet of 6-inch water service lines, valves, vaults, fire hydrants, pavement patching, concrete sidewalk removal and replacement, concrete curb and gutter removal and replacement, restoration, and all other incidental work.

Construction Limits

The project starts at the entrance to Arbor Drive from Algonquin Road, then east and south approximately 2, 060 feet, ending near the retaining wall for the I-53 ramp

Project Updates