2019 Street Reconstruction Program

   
Tentative Start Date: After June 1, 2019
Tentative Completion Date: 55 Working Days - approx. 4.5 months once started
Bid Opening: 03/12/2019
Project Manager: Bill Suchecki, RMPW Street Maintenance Superintendent
Contractor: Builders Paving, LLC
Awarded Contract Amount: $796,000.00
Funding Sources: Local

Project Information

The work to be performed consists of HMA pavement removal, full depth pavement reclamation and stabilization, aggregate base repair, HMA binder, HMA surface course, curb and gutter removal and replacement, sidewalk removal and replacement, driveway removal and replacement, drainage improvements and parkway restoration.


Construction Limits

Highland Drive (Quentin Road to Prairie Lane)

Prairie Lane (Highland Drive to Highland Drive)

Arlingdale Drive (Quentin Road to Kevin Lane)

Kevin Lane (Michael Court to Jessica Court)

Michael Court (Kevin Lane to Terminus)

Jessica Court (Kevin Lane to Terminus)

Reconstruction

Weekly Project Updates

Update as of 08/22/19:  Parkway restoration and concrete punch list work completed as of Wednesday, August 21, 2019.  Paving the final surface layer of asphalt is scheduled for Friday, August 23, 2019.  Fresh Oil application at 4am Friday, August 23rd.  PLEASE BE ALERT AND OBEY TRAFFIC CONTROL DEVICES, SIGNAGE AND FLAGGERS.