Tentative Start Date: | 5/20/22 |
Tentative Completion Date: | Early September |
Bid Opening: | 4/12/22 |
Project Manager: | Joel Benton, Rolling Meadows Public Works |
Contractor: | A Lamp Concrete Contractors, Inc. |
Awarded Contract Amount: | $1,027,232.89 |
Funding Sources: | Rebuild Illinois (RBI) & Local Road Fund |
The work to be performed consists of storm sewer improvements, curb and gutter removal and replacement, sidewalk removal and replacement, asphalt pavement removal, roadway base reclamation and stabilization, asphalt pavement replacement, parking bay improvements, pavement markings and parkway restoration.
Plum Tree Lane (Old Plum Grove to Emerson), Alder Cr. Croftwood Ct, Edgewood Ct, Green Meadows Ct, Heather Ct, Kimberry Ct, and Mayberry Ct.
Anticipated Hours of Work:
7:00 AM - 6:00 PM Mon - Fri; 8:00 AM - 5:00 PM Sat (If necessary)
Public Works Assistant Director
3900 Berdnick Street
Rolling Meadows, IL 60008
Email the Department
Phone: 847-963-0500
Fax: 847-963-0555
Hours
Monday - Friday
8 a.m. - 3:30 p.m.
3200 Central Road
Rolling Meadows, IL 60008
Hours
Open 24/7