Kirchoff Road Resurfacing

   
Tentative Start Date: April 2019
Tentative Completion Date: September 2019
Bid Opening: 11/09/2018 (IDOT Letting)
Project Manager: Bill Suchecki, RMPW Street Maintenance Superintendent
Contractor: Arrow Road Construction Company
Awarded Contract Amount: $2,073,879.34
Funding Sources: 80% State, 20% Local

Project Information

The work to be performed consists of HMA surface removal, Class B Concrete Patching, HMA level binder, HMA surface course, curb and gutter removal and replacement, sidewalk removal and replacement, drainage improvements, bridge deck wearing surface removal and replacement, detector loop replacement, median replacement and realignment from Hicks to Rohlwing, parkway restoration, and pavement markings.

Construction Limits

Kirchoff Road: 100' east of Hicks Road to 200' west of New Wilke Road

Rohlwing Road: 300' north of Kirchoff Road

E. Frontage Road: 250' south to Kirchoff Road

Owl Drive: 130' north of Kirchoff to 230' south of Kirchoff Road

Meadow Drive: 150' north and south of Kirchoff Road

kirchoff1

Weekly Project Updates

Update as of 08/20/19: Beginning on Wednesday, August 21st, Arrow Road Construction will be paving the final layer of asphalt surface on the outside lanes for eastbound and westbound Kirchoff Road.  ***Anticipated paving schedule as follows***:

Outside lane eastbound (Hicks to New Wilke) – Weds, August 21st  
Outside lane westbound (New Wilke to Hicks) – Weds, August 21st
Interior lane(s) eastbound (Hicks to New Wilke) – Weds/Thurs, August 21st-22nd
Interior lanes(s) westbound (New Wilke to Hicks)  - Thurs/Fri August 22nd-23rd
Adjoining sideroads – Friday, August 23rd  

Fresh Oil application to roadway surface will take place between 2am and 5:30 am Wednesday, August 21st.  

***This schedule is subject to change and is weather dependent***

PLEASE BE ALERT AND OBEY TRAFFIC CONTROL DEVICES, SIGNAGE AND FLAGGERS.