Fire Hydrant Painting

   
Tentative Start Date: July 1
Tentative Completion Date: August 2019
Bid Opening: MPI,  April 5, 2019
Project Manager: Jeff Stewart, Utilities Supervisor
Contractor: Alpha PaintWorks
Awarded Contract Amount: $19,575
Funding Sources: Local, Outside Repairs & Maintenance

Project Information

The City has contracted Alpha Paintworks to sandblast, prime, and paint 225 City fire hydrants during the 201Loading9 season. The Contractor will start the week of July 1st at the northeast corner of town (Cook County Court House) and work southwest, see map.  The project will take several weeks to complete, weather permitting.

Construction Limits

See Map



Click Map for Larger Image

Hydrant Painting Map

Weekly Project Updates

Week 7/1/2019, project has begun.