Fire Hydrant Painting

   
Tentative Start Date: September 2020
Tentative Completion Date: October 2020
Bid Opening: April 5, 2019 ( MPI 3 Year Contract)
Project Manager: Jeff Stewart, Utilities Supervisor
Contractor: Alpha PaintWorks
Awarded Contract Amount: $19,580
Funding Sources: Local, Outside Repairs & Maintenance

Project Information

The is year 2 of a multi-year program to sandblast prime and paint 225 of the 1469 Fire Hydrants within the City.  This is part of the City's annual fire hydrant maintenance program.

Construction Limits

The hydrants to be painted are north Euclid Ave. & west of Illinois Route 53 and the hydrants north of Kirchoff Rd. & east of Rohlwing Road.



Click Map for Larger Image

Hydrants

Weekly Project Updates


Construction Notifications