Plum Grove Drive/South Street Watermain Project

   
Tentative Start Date: May 2020
Tentative Completion Date: September 2020
Bid Opening: February 11, 2020
Project Manager: Jeff Stewart, Water Division
Contractor: Mauro Sewer Construction
Awarded Contract Amount: $1,298,804.00
Funding Sources: City Bonds

Project Information

Replacement of existing cast iron water mains with new PVC pipe water mains, including new water service connections and service pipe to each residence, fire hydrants and complete pavement and ground surface restorations.

Construction Limits

Plum Grove Drive from Magnolia to Barker and South Street from Meadow Drive to Dove Street.  Driveway and street access may be impacted during the project. Every effort will be made to keep interruptions as few as possible.  All residents will have access to their driveways by the of the work day.

On-street parking within the work zone is not permitted during hours of construction (M-F: 7am - 6pm).  Please park in your driveway or on adjacent streets not under construction to allow contractor activities to proceed with out delay.

Please place refuse & recycle carts at normal location for collection prior to 6:00 am on your regularly schedule day of the week.  Refuse will be picked up before the start of construction in you area.