- Home
- Government
- Departments
- Public Works
- Construction Projects
- Arbor Drive Improvements – Phase 1
Tentative Start Date: | Late August 2020 |
Tentative Completion Date: | October 2020 |
Bid Opening: | 4/28/2020 |
Project Manager: | Bill Suchecki |
Contractor: | Schroeder Asphalt Services, Inc. |
Awarded Contract Amount: | $ 295,586.70 |
Funding Sources: | CDBG (Cook County Community Development Block Grant) |
The work to be performed consists of storm sewer improvements, curb and gutter removal and replacement, asphalt surface removal, pavement base patching, asphalt leveling binder, asphalt surface course, and parkway restoration.
Arbor Drive (east leg) from IL Rt. 62 frontage to curve approaching I-90.
Anticipated Hours of Work: M-F: 7am to 5pm; Sat: 8am to 5pm (as needed)
Access Restrictions: Access to the parking lot for The Preserve of Woodfield may be limited at times within the construction limits. Please utilize entrances that remain open and accessible outside the construction limits should your normal entrance be temporarily inaccessible during construction.
Asphalt pavement milling and full depth pavement patching completed September 25, 2020. Binder course asphalt paving completed Saturday, September 26, 2020. Roadway frame adjustments completed September 29, 2020.
Fresh oil application and paving of the final layer of surface course asphalt scheduled for October 2, 2020.
Please be alert for construction personnel, equipment, and traffic.
Notify Me is a way residents can be updated via texts or e-mails of current construction projects.