The project consists of furnishing all materials, labor, and equipment required to install approximately 643 feet of 8-inch PVC sanitary sewer main line and approximately 185 feet of 6-inch sanitary service lines, manholes, cleanouts, pavement patching, restoration, and all other incidental work necessary to complete the second phase of this project required to provide sanitary sewer service to the residents living along Sunset to complete the Sunset/ Brookview area improvement.
Construction Limits
Weekly Project Updates