- Home
- Government
- Departments
- Public Works
- Construction Projects
- Hicks Euclid Bike Path
Hicks Euclid Bike Path
April 21, 2025 - Martam Construction has begun removing the existing sidewalk along Hicks Road, starting at Euclid Avenue. Driveway entrances impacted by the work are being temporarily backfilled with aggregate to maintain access until the new bike path is ready for installation.
April 26, 2025 - The removal of the existing sidewalk along Hicks Road has been completed, along with the removal of some grass and topsoil. Removal of the existing curb, gutter, and driveway entrances began on April 25 on Euclid Ave.. This work is ongoing and is expected to be completed by the end of the week.
May 5, 2025 - Contractor performed undercuts, Geotech fabric for ground stabilization, aggregate subgrade improvements, and aggregate base course work along the Euclid path alignment. Preparatory work for concrete curb placement on Euclid was also performed. Concrete placement on Euclid and storm sewer work on Hicks Road has begun this week.
May 13, 2025 - Martam continues progressing with the installation of stormwater pipes and structures along Hicks Road, with the majority of this work nearing completion. Crews have also begun laying the foundation for the new landscape wall.
Along Euclid Avenue, ADA-compliant sidewalks, curbs, and driveway entrances have been poured. The remaining concrete work is on track to be substantially completed by June.
Project Information
The Hicks road/Euclid avenue bike path project includes constructing an 8' wide bike path including storm sewers, retaining walls, curb and gutter work, sidewalk, ADA compliant pedestrian crosswalks, and traffic signal modifications. Project routing is on the west side of hicks road, from approximately 300 feet north of Kirchoff road to Euclid avenue, and on the north side of Euclid avenue from hicks road to countryside park, approximately 1000 feet west of hicks road. Total proposed project length is approximately 2700 feet (0.51 mi).
| Tentative Start Date | April 21, 2025 |
| Tentative Completion Date | Fall of 2025 |
| Bid Opening | January 17, 2025 |
| Project Manager | Brad Valentino, Street Superintendent |
| Contractor | Martam Construction Incorporated |
| Awarded Contract Amount | $1,051,892.50 |
| Funding Source | Local Road Capital, ITEP Grant |
.
Anticipated Hours of Work:
7:00 a.m.–6:00 p.m. Mon–Fri; 8:00 a.m.–5:00 p.m. Sat. (If necessary)
Contact Us
-
Aaron Grosskopf
Public Works Director
Public Works Department
3900 Berdnick Street
Rolling Meadows, IL 60008
Email the Department
Phone: 847-963-0500
Fax: 847-963-0555
Hours
Monday - Friday
7:00 a.m. - 3:30 p.m.
Recycling Center
3200 Central Road
Rolling Meadows, IL 60008
Hours
Open 24/7