Sanitary Sewer Point Repair

   
Tentative Start Date: TBD
Tentative Completion Date: 12/31/2022
Bid Opening: N/A
Project Manager: Mark Kilarski
Contractor: M.E. Simpson
Awarded Contract Amount: $14,000
Funding Sources: Utilities Fund

Project Information

There are 3 locations that were identified in need of corrective action (pipe replacement) in 2022 for the City’s sanitary sewer system. All three (3) point repairs where identified by way of our yearly televising program in accordance and compliance with the Metropolitan Water Reclamation District (MWRD) regulations. 

Construction Limits

The first repair is located at roughly 2707 Millstone Lane, the second repair at roughly 4451 Dawngate Lane, and the final repair at the intersection of Tall Oaks Lane and Richnee Lane.

Anticipated Hours of Work: 7AM- 4:00PM Monday- Friday

Weekly Project Updates:


Construction Notifications